Rangiora Fire Station
| CLIENT: | Hawkins |
| PROJECT: | Rangiora Fire Station |
| JOB TYPE: |
N/A |
| ESTIMATED DURATION: | 14 Days |
| VALUE: |
N/A |
DESCRIPTION:
Scope Demolition was contracted by the site developers to demolish Rangiora Fire Station, its associated structures and hard surfaces. Notable to this demolition was the presence of asbestos which was removed by our asbestos removal team prior to the hard demolition of the building. More asbestos was subsequently found, which involved the delicate hand removal of all windows and surrounding block work. All contaminated material was removed and disposed of under current MBIE regulations and the site decleared clear of all asbestos enabling the successful completion of the project.
